103.  This sub-process analyses the evaluation inputs by comparing them to the expected results and synthesises them into an evaluation report or control dashboard. The evaluation can take place at the end of the whole process (ex-post evaluation) and/or, for selected activities, be carried out during its execution in a continuous way, either as an ongoing evaluation or monitoring, thus allowing for quick fixes or continuous improvement. The resulting report should note any quality issues specific to this iteration of the statistical business process as well as highlight deviations of performance metrics from expected values, and should make recommendations for changes if appropriate. These recommendations can cover changes to any phase or sub-process for future iterations of the process, or can suggest that the process is not repeated.